CONTRACT CHANGE ORDER NO.3
Project No: 24101 Project Title: N Industrial Way Stormwater. Retrofit & Overlay
Contractor: Double J Excavating
Description of Change: Infiltration Trench Extension
Detail as Appropriate: It was necessary to extend the length of the infiltration trench 15' to ensure
that flows were adequately handled. This involves crossing an existing
gas service line.
Contract Bid Amount: $ 503,000.00
SALES TAX @ 8.7%: WA
Total: $ 503,000.00
PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER
Subtotal $ 3,166.35 Subtotal $ 5,240.00
Sales tax @ 8.7% NIA Sales tax @ 8.7% N/A
Total $ 3,166.35 Total $ 51240.00
Total Change Orders To Date $ 8,406.35
New Contract Amount $ 1511,406.35
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER r—Y-E-6-1 NO
Contract Time Prior to this Change Order ................_.............. . 41
Modification to Contract time by this Change Order .................... 1
revised Total Contract Time .................................................... 42
it is mutually agreed by both parties that this Change Order fully describes the change(s) that Is (are)
being made and that the compensation for this Change Order is full and complete and is the only
compensation due or owing for this Change Order. Further, it is mutually agreed that this document will
supplement the present Contract Documents and that the provisions of the previously executed Contract
Documents shall apply to this Change Order.
AGREED TO AND ACCEPTED: APPROVED:
CONTRACTOR Da MOJECT MANAGER Dabs
APPROVED: D'
5 -JZ •2Z C
DData—-��
T. MANAGER ate b? DIRECTOR
Dais --
F
DOUBLE J
Fxrmienmr.
TO: City of Pasco
Attn: Dan Pratt
CHANGE PROPOSAL
CP:
#03
DATE: May 10, 2022
PROJECT NAME: N. Industrial Way Stormwater Retrofit & Overlay Project (No. 20-101)
DESCRIPTION: Infiltration Trench Extension
This Change Proposal addresses the request by the City of Pasco to extend the infiltration trench at
29+00.
DESCRIPTION QTY U/OM RATE TOTAL
1— Mobilization 1 LS $ 1,000.00 $ 1,000.00
10— Underdrain Pipe Infiltration Trench
System 12 In. Diam. 20 LF $ 211.00 $ 4,220.00
11— Shoring or Extra Excavation 20 LF $ 1.00 $ 20.00
TOTAL COST $ 5,240.00
ADDITIONAL WORKING DAYS REQUIRED:
EXCLUSIONS: Engineering, Solid Rock Hammering/Removal, Utility Company Fees, Apprenticeship Requirements, Overtime Premiums,
Sales Tax, and/or Permits.
This Change Proposal, when accepted, becomes part of the Project Contact/Agreement. This Change Proposal is considered accepted when work is
performed in relation this Change Proposal. Payment in full is due upon completion. Interest may accrue on all invoices that are past due at the rate of 1 %%
per month (18% per annum) until paid in full.
Respectfully submitted,
Cameron Mensonides
DOUBLE J EXCAVATING, INC.
2564 ROBERTSON DRIVE • RICHLAND, WA 99364 • (509) 627-2030 • (509) 352-6744 FAx
WASHINGTON CONTRACTOR NUMBER: DOUBUE832LL
OREGON CCB NUMBER: 231388
PAGE 1 OF 1