HomeMy WebLinkAboutDouble J Excavating - N Industrial Way Stormwater Retrofit & Overlay - Change Order No. 1 (20101)CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO.1 Project No: 20101 Project Title: N Industrial Way Stormwater Retrofit & Overlay Contractor: Double J Excavating Description of Change: Remove Existing Catch Basin & Curb Detail as Appropriate: Changes at the gallery at STA 29.50, to Include removal of existing catch basin and curb Contract Bid Amount: $ 503,000.00 SALES TAX @ 6.7%: N/A Total: $ 503,000.00 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER (Subtotal Subtotal $ 1,277.65 Sales tax Q 8.7% WA Sales tax @ 8.7% WA Total $ - Total $ 1,277.65 Total Change Orders To Date $ 1,277.65 New Contract Amount $ 504,277.65 1S CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO Contract Time Prior to this Change Omer ................................. 40 Modification to Contract time by this Change Order....................1 revised Total Contract Time .................................................... 41 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: CON RACTOR Date APPROVED: PROJECT MANAGER DMe DOUBLE J EXCAVATING TO: City of Pasco Attn: Dan Pratt CHANGE PROPOSAL CP: #01 DATE: April 20, 2022 PROJECT NAME: N. Industrial Way Stormwater Retrofit & Overlay Project (No. 20-101) UtbLKI r I IUN: Lnanges io vanery al Z10 I A cy-1-OU This Change Proposal addresses the changes at the Gallery at STA 29.50. To Include the removal of existing catch basin and curb. 1. Additional labor, equipment & materials. DESCRIPTION QTY U/OM RATE TOTAL 1. Remove Existing CB & Curb 1 LS $1,150.00 $1,150.00 Subtotal $1,150.00 Markup (10%) $ 115.00 Total $1,265.00 Bond Rate (1%) $ 12.65 TOTAL COST $1,277.65 ADDITIONAL WORKING DAYS REQUIRED: 1 EXCLUSIONS: Surveying/Layout, Engineering, Solid Rock Hammering/Removal, Utility Company Fees, Apprenticeship Requirements, Overtime Premiums, Sales Tax, and/or Permits. This Change Proposal, when accepted, becomes part of the Project Contact/Agreement. This Change Proposal is considered accepted when work is performed in relation this Change Proposal. Payment in full is due upon completion. Interest may accrue on all invoices that are past due at the rate of 1 per month (18% per annum) until paid in full. Respectfully submitted, Cameron Mensonides DOUBLE J EXCAVATING, INC. 2554 ROBERTSON DRIVE • RICHLAND, WA 99354 • (609) 627.2030 • (509) 352-6744 FAX WASHINGTON CONTRACTOR NUMBER: DOUBUE832LL OREGON CCB NUMBER: 231388 PAGE 1 OF 1