HomeMy WebLinkAboutApollo, Inc. - WPWTP Improvements, Ph 1 - Change Order 1 (16-008)CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO.1 Project No: 16 008 Project Title: WPWTP Improvements, Phase 1 Contractor: Apollo, Inc. Description of Change: Access Roadway Work Detail as Appropriate:18_11G-pip aii New Access Roadway to WTP site from Rd. 111 Contract Bid Amount: $ 7,745,700.00 SALES TAX @ 8.6%: $ 666,130.20 Total: $ 8,411,830.20 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal Subtotal $ 8,385.09 Sales tax @ 8.6% $ - Sales tax @ 8.7% $ 729.50 Total $ - Total $ 9,114.59 Total Change Orders To Date $ 9,114.59 New Contract Amount $ 8,420,944.79 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO Contract Time Prior to this Change Order ................................. 300 Modification to Contract time by this Change Order .................... 0 revised Total Contract Time .................................................... 300 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: APPROVED: ���-- Amy Jenne ��ti,"� 4/1/22 CONTRACTOR Date PROJECT MANAGER Date Pasco I Wa hnWm CHANGE ORDER NO. 001 PROJECT: West Pasco Water Treatment Plant Expansion: Phase 1 DATE OF ISSUANCE: 03/17/2022 OWNER: City of Pasco BID ITEMS: In any involved CONTRACTOR: Apollo, Inc. ENGINEER: RH2 Engineering, Inc. You are directed to make the following changes in the Contract Documents. Description: Access roadway work Documents Supporting Changes: See CPR attached Original Contract Price: $8,411,830.20 Previous Approved Change Order(s): None Total of Previous Change Orders: $0 Change Order(s) approved this Form: CO #001 Total of Change Order(s) Approved this Form: $9,114.59 ($8,385.09 Lump Sum Cost + $729.50 Sales Tax) Contract Price with all Approved Change Orders: $8,420,944.79 RECOMMENDEDA,:� APPROVED: By By Engineer - Contractor Original Contract Time: 300 days Net Change Approved from Previous Change Orders: 0 Contract Time Prior to the Change Order: 300 days Net Increase (Decrease) of this Change Order: 0 Contract Time with All Approved Change Orders: 300 days APPROVED: By Owner By signing this form, the Owner and the Contractor agree to release all claims to additional work or credit or delays, occurring prior to the Date of Issuance, which have not been identified in this Change Order form. 04/01/22 7:58 AM J:\Data\PSC\20-0062\60 SDC\Change Orders\CO 001 - Access Road\WPWIT Expansion Ph1 - CO 01.docx Contractor Proposal Request Project: West Pasco WTP Phase 1 Apollo Inc. Date: 03/14/22 I Description ■ Labor I I Mat I I Equip. I I Subcont. Total I I Supp Total I I Total I Access Roadway' $ 1,018.90 $ 4,453.61 $ 1,627.85 $ 1,076.40 $ 50.95 $ 8,227.70 SUBTOTAL COST > $ 8,227.70 Insurance Premium .5% -Changed Work> $ 58.66 Bond Premium 1.2% - Changed Work > $ 98.73 TOTAL LUMP SUM COST > $ 8,385.09 Print Date: 3/31/2022 Page 1 of 1 CPR 001 Access Road