HomeMy WebLinkAboutRH2 Engineering, Inc.- East UGA Expansion Sewer LID PSA (#22-002) - Amendment No. 1AMENDMENT NUMBER 1 to
PROFESSIONAL SERVICES AGREEMENT
East UGA Expansion Sewer LID
Project No. 21295
AGREEMENT NO. 22-002
WHEREAS, the City and RH2 Engineering, Inc. (RH2), entered into a Professional
Services Agreement (PSA) on 1/21/2022 to provide engineering services with respect to the
City's East Urban Growth Area (UGA) Expansion Sewer Local Improvement District (LID)
project; and
WHEREAS, the initial scope of work included in the original PSA was purposefully
limited to begin work as soon as possible and include enough design work and public
involvement to allow for the successful formation of the LID through Council approval; and
WHEREAS, the LID is now formed and final design and development of sewer and lift
station bid packages can move forward; and
WHEREAS, RH2 completed the work identified in the original agreement not utilizing
all funds allocated for that work; and
WHEREAS, RH2 and the City would like to use the unused funds from the original
agreement to complete the work proposed in Exhibit A; and
WHEREAS, executing this `no cost' change order allows the work described in Exhibit
A to begin upon execution.
NOW, THEREFORE, this agreement is amended to allow RH2 Engineering, Inc., to
provide continued professional (design) engineering services as described on Exhibit A.
1. Scone of Work:
See Exhibit A.
2. Fee:
No Change. This is a $0.00 amendment. Original authorization was based on Time &
Materials Basis and was in the amount of $270,045.00.
Time ofperformance:
No Change. The services shall be complete for the project on or before 12/31/2023.
DATED THIS 5^fih DAY OF A 0 y101 , 2022.
CITY OF PASCO: CONSULTANT
vv t- V
City of Pasco
Steve M. Worley, PE — Public
Works Director 7
Amendment No. I to Professional Services Agreement
RH2 Engineering, Inc.
East UGA Expansion Sewer LID
RH2 Engineering, Inc.
Paul Cross, PE — Principal
Page I
EXHIBIT A
Scope of Work
Amendment No. 1
City of Pasco
East UGA Expansion Sewer Local Improvement District Project
(No Cost Change)
Early Action Phase 3 Items
August 2022
Background
The City of Pasco (City) has retained RH2 Engineering, Inc., (RH2) to design gravity sewer transmission
mains and one sewer pump stations to connect the expanded Urban Growth Area (UGA) east of Road
68 and the Reimann Industrial Center (RIC) to the existing sewer system. The City's preliminary design
concepts call for a 12- and 15 -inch -diameter gravity sewer main, up to two (2) lift stations and up to
three (3) major crossings of either Burlington Northern Santa Fe (BNSF) Railway or State Route 395
(SR 395) through the Washington State Department of Transportation (WSDOT). Much of the route
will require new easements and/or permits with Franklin County (County) to construct along the
existing County right-of-way (ROW).
Phase 1 of the project focused on assessing the preliminary alignments proposed in the Addendum
to the Comprehensive Sewer Plan (Sewer Plan) and progressing the design to a point where a local
improvement district (LID) can be formed to provide services to the East UGA.
Phase 2 of the work identified high priority early -action items necessary to proceed with easement
acquisitions and rights of entry as soon as the agreement to form the LID is determined and the UGA
is confirmed by Growth Management Hearings Board. A contract amendment for Phase 3 will be
required to prepare final design plans, technical specifications, and cost estimates for gravity sewer
pipelines, lift stations, and force mains for those portions of the project that are ready to proceed.
Additional phases may be required for those areas that are not ready to address their development
needs and construction contracts are anticipated to be broken out into multiple schedules with some
schedules bid together and others bid separately.
The fee for subconsultant services identified in Phase 1 and Phase 2 included some of the
subconsultant fees for geotechnical, cultural, and survey. As the amendment for Phase 3 is prepared,
the schedule now dictates that additional subconsultant work be done in Phase 2 than was originally
contemplated. The intention of this amendment is to authorize additional early action subconsultant
services and offset those costs by deferring some RH2 labor and expenses until the Phase 3 contract
is approved. The net result is a no -cost change to the currently approved contract.
City of Pasco Amendment No. 1
East UGA Expansion Sewer LID Project Exhibit A — Scope of Work
Task 1— Early Action Phase 3 Items
Objective: Subcontract and coordinate work in the areas of topography surveys, cultural
assessments, and geotechnical evaluations necessary to prepare for the design schedule
contemplated in Phase 3.
Approach:
1.1 Subcontract and coordinate with Aspect Consulting, LLC (Aspect) to perform geotechnical
drilling, investigations, and reporting at the proposed force main crossing at State Route 395
and Foster Wells Road as well as investigating the proposed lift station site on the west side of
Glade Road at Burns Road extended.
1.2 Subcontract with Plateau Archeological Investigations, LLC (Plateau) to perform cultural
investigations of the area from the BNSF right of way west along Clark Road extended; then
south along North Glade Road to Burns Road extended; then east along the force main route to
North Railroad Avenue, Northern Street, Burlington Street, and Foster Wells Road to North
Capital Avenue. This investigation will include the lift station site on the west side of Glade Road
at Burns Road extended.
1.3 Subcontract with Rogers Surveying, Inc., (Rogers) to perform topographic surveys from the
BNSF right of way west along Clark Road extended; then south along North Glade Road to Burns
Road extended; then east along the force main route to North Railroad Avenue, Northern
Street, Burlington Street and Foster Wells Road to North Capital Avenue. This survey will include
the lift station site on the west side of Glade Road at Burns Road extended.
Assumptions:
• This amendment will be a no -cost change to the current contract. The additional cost of
subconsultant work authorized for early action will be offset by deferring design and
permitting services contemplated in this contract to a future Phase 3 contract by substitution.
• Surface features within BNSF ROW and SR 395 ROW will not be needed for the design since
trenchless construction will be performed in those areas at depths where existing surface
features will not be disturbed.
• The right of entry documents previously obtained by the City are valid for the subconsultant
work listed in this Scope of Work.
Provided by the City:
• Confirmation of right of entry with private landowners.
RH2 Deliverables:
• Geotechnical drilling logs and report by Aspect in electronic PDF.
• Cultural report, Inadvertent Discovery Plan, and initial consultation letters for Washington
State Department of Archaeology and Historic Preservation and the tribes by Plateau in
electronic PDF.
• Topographic maps of project areas by Rogers in AutoCAD format.
2
EXHIBIT B
Fee Estimate
Amendment No. 1
City of Pasco
East UGA Expansion Sewr LID Project - Early Action Phase 3 Items
Jul -22
Total
Total Labor
Total Subconsultant
Total Expense Total Cost
Description Hours
Task 1 Early Action Phase 3 Items 1 $ (74,253)1 $ 77,907 1 $ (3,654) $ 0
PROJECT TOTAL 1 405 1 $ (74,253)1 $ 77,907 1 $ (3,654) $ 0