HomeMy WebLinkAbout4601 Ordinance - 2021-2022 Supplemental Budget Fire Station No. 85 Site Work ORDINANCE NO. 4601
AN ORDINANCE AUTHORIZING THE EXPENDITURE OF BOND
REVENUE FOR THE PURPOSE OF FINANCING THE CONSTRUCTION
COSTS ASSOCIATED WITH THE FUTURE PASCO FIRE STATION NO. 85
SITE WORK PROJECT AND AMENDING THE 2021-2022 BIENNIAL
BUDGET GENERAL CONSTRUCTION FUND.
WHEREAS,on December 7,2020,the Pasco City Council approved Ordinance No.4503,
adopting the 2021-2022 Biennial Budget; and
WHEREAS, on November 22, 2021, the Pasco City Council approved Ordinance No.
4560, adopting the 2021-2022 Mid-Biennium Budget Adjustment amending the 2021-2022
Biennial Budget; and
WHEREAS, the 2021-2022 Mid-Biennial Budget included $527,230 for work related to
the design of Fire Station No. 85; and
WHEREAS, to meet current and projected growth in the northwest area of Pasco an
additional Fire Station is needed; and
WHEREAS, the first phase of the project has been determined to include site work to
prepare for future construction; and
WHEREAS, the lowest bid of$1,002,344.52 from C& E Trenching LLC was accepted
by City Council at their May 2, 2022, meeting; and
WHEREAS, the City Council finds that sufficient funds exist from the prior sale of City
bond(s), which bonds having been duly authorized by the City Council, and are available to fund
the construction costs of this project and such expenditure being consistent with 35A.34.200(1)(c)
and in the best interest of the City of Pasco, as it ensures successful and timely completion of a
necessary Capital Improvement Project, it is hereby authorized by the City Council of the City of
Pasco.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF PASCO,
WASHINGTON DO ORDAIN AS FOLLOWS:
Section 1. Pursuant to RCW 35A.34.200(1)(c), the funding of the construction costs
related to the C&E Trenching project shall be financed through the revenues earned through the
sale of duly authorized City bond(s) and the 2021-2022 Mid-Biennial Budget shall be amended
to include these additional revenues within the General Construction Fund with the following end
fund balance:
Ordinance—2021-2022 Capital Project Budget Amendment
Future Fire Station No. 85 Site Work Project- 1
Fund EXPENDITURE REVENUE
GENERAL CONSTRUCTION FLTND $1,002,344 $1,002,344
GENERAL FUND (RESTRICTED GO BONDS) $1,002,344
Total $2,004,688 $1,002,344
Section 2. That the additions in appropriations and expenditures are hereby declared to
exist in the above funds for the said uses and purposes as shown above, and the proper City
officials are hereby authorized and directed to issue warrants and transfer funds in accordance
with the provision of the Ordinance.
Section 3. Except as amended herein, Ordinance No. 4560 as previously adopted
heretofore shall remain unchanged.
Section 4. This Ordinance,being an exercise of a power specifically delegated to the City
legislative body, is not subject to referendum, and shall take full force and effect five(5) days after
approval, passage and publication as required by law.
PASSED by the City Council of the City of Pasco,Washington this 18�'day of July, 2022.
r ��
Blanche Barajas
Mayor
ATTEST: APPRO AS O FORM:
��� �
�
Debra Barham, CMC Kerr guson Law, PLLC
City Clerk ' Attorneys
Published: c, 1�1 2( �Z-�-
Ordinance—2021-2022 Capital Project Budget Amendment
Future Fire Station No. 85 Site Work Project-2